Virginia
Fairfax County checks a private soil evaluator, and shallow systems wait on rainfall
Fairfax County does not run the first soil test. You hire a soil scientist or an onsite soil evaluator, file in the PLUS system, and the health department goes out to check that work. For a shallow system, the month has to be wet enough.
Last verified against the county pages linked below. Fees and seasons change. The office on the application is the authority.
The county's trip is a check, not the first test
Fairfax County Health Department's sewage page says the site work starts when the homeowner hires a local soil scientist, files in PLUS, and an environmental health specialist visits to review that evaluation. The inspection page is more specific. Before any onsite system is approved, the department does a Level 2 onsite assessment to validate the onsite soil evaluator's or engineer's submission. A separate perc check verifies the private testing method. A later septic-layout inspection, before the construction permit, confirms the site still matches the plan.
Chapter 68.1 defines a soil evaluation as both the surface and the profile: landscape position, slope, drainage, disturbance, and stoniness, plus color, texture, consistency, rock, and seasonal and permanent water tables. The private report is the evaluation. The county visit is how the health department decides whether to trust it.
Shallow systems depend on the rain record
The ordinance says every proposed shallow onsite system has to be evaluated in a month that meets or exceeds the long-term monthly composite average rainfall from Dulles and from Reagan National. Water-table monitoring wells, when the evaluation needs them, are read in those same months. The health department repeats that rule on its program page. It does not publish a permanent list of passing months, because the test is a comparison with the long-term average, not a season written into the code.
Depth changes the test. Hydraulic conductivity is required, along with the profile holes, when the proposed installation is shallower than 18 inches. At 18 inches or deeper, percolation testing under Appendix G of the state regulations is allowed. A shallow or surface bed needs at least 16 profile holes on 25-foot centers inside a 100-by-100-foot grid, bored two feet deeper than the estimated trench depth. Peat modules are decided case by case. At least five conductivity sites or perc holes are required. Any area where a hole is slower than 120 minutes per inch, for installations at or deeper than 12 inches, or slower than 45 minutes per inch, for installations shallower than 12 inches, is void.
Eighteen months, and a county fee that is not the state fee
The county fee table lists a new sewage-disposal application, for a flow of 1,000 gallons a day or less, at a $200 county fee, a $215 state fee, a $200 county plan-review fee for an alternative system, and a $10 state indemnification fee. A certification letter at that flow is a $310 state fee plus $10, and another $200 county application fee. Flows over 1,000 gallons a day show a $1,390 state fee on the same table. The private evaluator's charge is not on the table. The ordinance says the county fees are in addition to whatever the Commonwealth charges, and that a repair of a malfunctioning system has no county fee.
The same ordinance adopts the state permit section with a local edit: the construction permit is valid for 18 months and can be revalidated in writing for another fee. If the site or the proposal changes enough to need a new evaluation, you file again and pay again. Probing appointments wait at least three working days for utility marks. The program phone is 703-246-2201, and the filing system named on the page is PLUS.
File the private report, then wait for utility marks
- Hire a local soil scientist or onsite soil evaluator before you file. The health department reviews that work; it does not replace it.
- For a shallow system, check whether the month meets the long-term rainfall average at Dulles and National. The county does not print a standing calendar.
- Plan on at least five percolation holes or hydraulic-conductivity tests. Shallow and surface beds also need a grid of at least 16 profile holes on 25-foot centers.
- File in PLUS and pay the county fee. State certification and indemnification fees are separate lines on the county table.
- If staff will probe or auger, do not expect an appointment inside three working days. That gap is for utility clearance.
Start here: Onsite sewage and private wells. Phone 703-246-2201. Or compare this county with the others in the county requirements tool.
Montgomery County, next door, still runs the perc test itself
- Montgomery County, Maryland: county inspector, county perc test, after a water-table test.
- Wake County, North Carolina: county staff, county soil and site visit.
- Boulder County, Colorado: engineer or geologist, soil profile pits.
Rainfall season and private evaluators, explained once
- Perc test vs. soil evaluation: what's the difference?
- When to schedule a perc test (and seasonal limits)
- How to prepare for a perc test