Georgia

Gwinnett County wants a Level 3 soil report before the health department visits

Gwinnett County Environmental Health will not start a new septic permit, a repair, or an addition that changes the system until a certified soil classifier's Level 3 report is in the file. The county visit comes after that report. The 2026 residential bundle for the evaluation, the permit, and the first inspection is $275.

Last verified against the county pages linked below. Fees and seasons change. The office on the application is the authority.

By C. V. Wooster, Taciturn Studios · Updated November 21, 2026 · How we research

The soil report comes first

GNR Health, which covers Gwinnett, Newton, and Rockdale, posted that as of February 7, 2022 every one of its environmental health offices requires a Level 3 soil report before a septic permit for new work, a repair, or an addition that modifies the system. The Gwinnett residential instructions repeat it. If an approved Level 3 report is already on file, it can be reused. If it is not, the application needs an original stamped report from a certified soil classifier the state recognizes. The form sends you to the Department of Public Health list at dph.georgia.gov/wastewater-management.

That is a different sequence from a county that digs perc holes on request. The classifier describes the soil. Environmental health reviews the package and makes a site visit. After that review, staff may decide the lot needs an engineered site plan, which the form says is typical when the lot is tight. They may also ask for a Level 4 report when an alternative system is proposed or they need more soil data. The application does not describe a homeowner perc test, and the fee schedule does not have a percolation-test line.

Ten working days, and a $275 residential bundle

The new-construction instructions say to allow the office 10 working days to review the plans and conduct the site visit. That is the only turnaround the form states. It is working days, and it covers both the paper and the visit.

The Gwinnett fee schedule adopted August 25, 2025 and effective January 1, 2026 lists site evaluation, permit, and initial inspection for a residential system at $275. The commercial equivalent is $600. An addition that does not modify the septic system is a category 1 site evaluation at $150. A visual inspection of an existing system is $145. Reinspection is $175, and sending plans back is $125. Installing without a permit is twice the permit fees. The classifier's fee is not on this schedule.

The sketch is part of the application

For a new house that does not already need an engineered plan, the form asks for four things: the completed application and fee, a lot sketch, the Level 3 report, and a floor plan. The sketch has to be at least 1 inch equals 40 feet, show lot dimensions, the building to scale, the road, wells or water within 100 feet of the lines, and the driveway, patio, deck, sidewalk, shed, and other pavement, plus underground utilities and the plumbing stub. The floor plan labels every room on every story and does not have to be drawn to scale.

Gwinnett's phone on the GNR form is 770-963-5132. Newton and Rockdale have their own numbers and their own fee schedules. A Gwinnett lot pays the Gwinnett line. Nothing on the form or the 2026 fee sheet sets a seasonal testing window or a number of years a soil report stays valid. Both of those, if you need them, are questions for the office rather than figures this page should invent.

Get the classifier's stamp in the file first

Start here: GNR septic systems. Phone 770-963-5132. Or compare this county with the others in the county requirements tool.

A county that still digs perc holes

Soil reports versus a timed perc hole

The GNR fee schedule and the residential application

  1. Gwinnett environmental health fee schedule, effective January 1, 2026
  2. Septic systems, including the Level 3 notice
  3. Residential new-construction application