Larimer County inspects two pits and treats a perc test as optional extra data
Larimer County will not take a perc rate in place of soil pits. Since June 4, 2018 the county has required two test pits, left open for inspection, with the evaluation done by a professional engineer or under that engineer's supervision. A percolation test can be added. It cannot replace the pits.
Last verified against the county pages linked below. Fees and seasons change. The office on the application is the authority.
Two pits are the requirement
The county's septic page says that since June 4, 2018 every application for a new on-site system has to include an inspection of two test pits. You may also submit percolation results, and if you do they are in addition to the pits. The pits stay open for Larimer County and for the engineer or designer. Cover them with fencing or stakes. The page describes pits 8 feet deep, or shallower at groundwater or bedrock, with a bench at 4 feet and a slope of about 45 degrees so someone can enter the bench. They generally sit 40 to 50 feet apart in the soil treatment area.
The 2026 regulations say a percolation test is not a substitute. In addition to the two profile pits, perc testing may be used for more information about the long-term acceptance rate. If the pit evaluation and the perc test point at different rates in the state's table, the designer uses the more restrictive one. Profile observations happen before any perc test, so the evaluator knows whether the soil is worth testing and at what depth. When a perc test is run, the regulations call for at least three holes, 8 to 12 inches across, ended between 6 and 18 inches below the proposed infiltrative surface. The presoak holds at least 12 inches of water for at least four hours, preferably overnight, and the rate is read 24 hours after water is first added. Type 1 sand can be read after one filling drains. The department can require a longer presoak for some county soil types.
Both county documents total a new permit at $1,881
The 2026 environmental-health fee table, effective January 1, 2026, lists a new OWTS permit at $1,881 and notes that the figure includes a $20 Colorado Department of Public Health and Environment surcharge. The application PDF lists the same $1,881 total and splits it as $1,858 plus a $23 surcharge. A major repair or remodel is $1,320 on both. A minor, tank-only repair is $750. This page reports the shared total and does not pick a winner between the $20 and $23 surcharge lines.
A separate site evaluation is $290, and only when the pits have to be inspected and backfilled before you apply. If they can stay safely open, the county inspects them during the permit review and does not add that fee. A return trip is $205. An owner who installs the system adds $345, and the application form says an engineer-designed system may not be self-installed. The form also says an engineer's design is required when the perc rate is outside 5 to 60 minutes per inch, the soil is coarse or rocky, bedrock or groundwater is within 4 feet of grade, the system uses pressure distribution, or the slope is over 30 percent.
One year, unless no building permit is involved
The 2026 regulations say the permit expires one year after issuance if construction has not started. When a building permit and an OWTS permit are issued together, the OWTS permit also expires if the system is not started before the building permit expires. On a property that does not need a building permit, the OWTS permit expires 180 days after issuance if construction has not started. An extension has to be requested at least 30 days before expiration, and extra inspection fees apply if the design or the location changed.
The septic page says applications and documents can be submitted online or dropped off at the Fort Collins or Estes Park offices, with the fee paid at submittal. The PDF application still says applications must be made in person and lists the fee at the top of the form. Those two instructions are both on county URLs. Follow the septic-systems page and confirm the counter before you drive. A separate site-evaluation inspection, when you need one, takes at least five business days to arrange. The county does not publish a day count for ordinary permit review.
Keep the benches safe until the county looks
- Have a professional engineer, or someone working under that engineer, evaluate the soil. Two pits are required.
- Dig the pits in the soil treatment area, generally 40 to 50 feet apart, 8 feet deep or to groundwater or bedrock, with a bench at 4 feet and a 45-degree slope back to grade.
- Leave the pits open, fenced or staked, so the county and the engineer can inspect them during the permit review.
- If the pits cannot stay open, request a site evaluation and pay $290. The county says that inspection takes at least five business days to schedule.
- Add a perc test only as extra information. If you do, the regulations want at least three holes, and the slower of the pit-based rate and the perc rate is the one that sizes the system.
Start here: Septic systems (OWTS). Or compare this county with the others in the county requirements tool.
Boulder County's permit is priced differently
- Boulder County, Colorado: engineer or geologist, soil profile pits.
- Washtenaw County, Michigan: county evaluation, with the design engineer, backhoe soil pits.
- Wake County, North Carolina: county staff, county soil and site visit.
How a profile pit and a perc hole differ
- Perc test vs. soil evaluation: what's the difference?
- The septic permit process, step by step
- How to prepare for a perc test